試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project team has just completed the development of a new order tracking system. The project sponsor, the director of sales, is pleased with the new system. However, the director of manufacturing is not pleased and has demanded that the system be re-designed to meet manufacturing concerns. The project manager estimates that a system redesign will delay implementation by two months.How could the project manager have avoided this situation?
A、Completed a roles and responsibility matrix in the planning phrase.
B、Involved key stakeholders to ensure that requirements were not overlooked.
C、Ensured that the director of sales had approved the requirements.
D、Developed an effective project scope and change control process during project planning.